CHANGYUAN POWER announced that its wholly-owned subsidiary Guoneng Changyuan Gucheng New Energy Co., Ltd. has adjusted the planned installed capacity of the 50MW agricultural-photovoltaic complementary power generation project in Shengkang Town, Gucheng County from 50,000 kilowatts to 47,900 kilowatts. The dynamic total investment of the project has been adjusted from 259 million yuan to 216 million yuan. As of May 31, 2025, the actual effective usable land area of the Shengkang photovoltaic project is 1,387 acres, with a total of 19 power generation units arranged, completing a grid connection of 47,900 kilowatts