TSMC’s 1.4nm fab is far ahead of schedule, media report:

-First 1.4nm fab seen finished by April 2027

-Pilot production to begin early in the 3rd quarter, 2027

-Mass production is on track for mid-2028.

-Construction remains ongoing at the 1.4nm fab in the Central Taiwan Science Park (CTSP) near Taichung.

-TSMC is also investing NT$100 billion on 2 advanced packaging plants nearby in CTSP’s Erlin Park $Taiwan Semiconductor(TSM.US) $Apple(AAPL.US) $NVIDIA(NVDA.US) $Qualcomm(QCOM.US) $Alphabet(GOOGL.US) #semiconductors

Source: Dan Nystedt

The copyright of this article belongs to the original author/organization.

The views expressed herein are solely those of the author and do not reflect the stance of the platform. The content is intended for investment reference purposes only and shall not be considered as investment advice. Please contact us if you have any questions or suggestions regarding the content services provided by the platform.