ChangGao NEET: The Jinzhou Phase III project and two other projects will commence construction successively
ChangGao NEET stated in a conference call on April 29 that the Jinzhou Phase III project includes a clean workshop for 1000kV GIS equipment and complete gas-insulated switchgear products, with plans to start construction in June this year and begin production next year. The GIL assembly workshop is planned to start production by the end of this year. The Wangcheng quality improvement and renovation project is scheduled to commence in July and begin production in mid-next year. The Hengyang transformer production base is planned to start construction in the third quarter of this year and be operational by the end of next year. All three projects will commence successively, with initial investments made using self-owned funds