HEGC: It is expected that the company will add 1 million kilowatts of new installed capacity for the whole year of 2025
Hubei Energy stated at the performance briefing that it expects to add 1 million kilowatts of new installed capacity for the entire year of 2025. The company's current major projects under construction include three pumped storage projects, the second phase of the Jiangling Power Plant thermal power project, and the 150MW wind power project in Hedong, Yicheng. Among them, the Luotian Pingtanyuan pumped storage project is expected to have all units put into operation by 2028; the Changyang pumped storage project is expected to have all units put into operation by 2030; the Nanzhang Zhangjiaping pumped storage project is expected to have all units put into operation by 2030; the second phase of the Jiangling Power Plant thermal power project is expected to have all units put into operation by 2026; and the 150MW wind power project in Hedong, Yicheng is expected to be fully operational by December 2025