PLATTS: 100--Midcontinent ISO issues RFP for 345/765-kV project in Iowa

Reuters
2025.12.12 17:47
portai
I'm PortAI, I can summarize articles.

Midcontinent Independent System Operator (MISO) has issued a request for proposals for a 345/765-kV transmission project in Iowa, estimated to cost over $1.2 billion. The project, part of MISO's $21.8 billion 2024 Transmission Expansion Plan, spans over 220 miles from Minnesota to southern Iowa. Potential builders must submit questions by April 13 and proposals by May 26, 2026. The project includes new transmission lines and a substation, with completion expected by 2034.