新纪元能源从美国能源部获得 19 亿美元贷款,以重启杜安·阿诺德核电站

ZeroHedge
2026年9月10日 01:46
LongbridgeAI我是 LongbridgeAI,我可以总结文章信息。

新纪元能源获得了美国能源部 19 亿美元的贷款,以重启位于爱荷华州的杜安·阿诺德核电站。该项目得到了与谷歌签署的为期 25 年的电力购买协议的支持,预计将在 2029 年开始供电。这是美国核电重启的第三笔 EDF 贷款,此前支持了三里岛和帕利塞德核电站。该倡议旨在恢复美国在核能领域的领导地位,降低电力成本,并创造就业机会

By Zachary Skidmore of DataCenterDynamics

NextEra Energy has secured a $1.9 billion loan from the US Department of Energy’s Office of Energy Dominance Financing (EDF) to support the restart of the Duane Arnold nuclear power plant, which is tied to a long-term Power Purchase Agreement (PPA) with Google.

The plant, located in Linn County, Iowa, is the only nuclear energy project in the state and first entered service in February 1975. However, due to the 2020 Midwest derecho (straight-line windstorm), which damaged the facility’s cooling towers, repairs were deemed uneconomical, leading to its shutdown.

Duane Arnold Energy Center in Linn County, Iowa

Reports surfaced in 2024 that NextEra was considering a restart of the 615MW plant, following Microsoft's announcement that it would take 100 percent of a revived Three Mile Island nuclear power plant in Pennsylvania. The company subsequently announced that it had signed a 25-year PPA with Google in October, with the plant expected to begin delivering power by 2029.

According to the DOE, the latest loan will help finance the restart of the plant and represents the third loan provided by EDF to support a nuclear plant restart in the US. These include the Crane Clean Energy Center (Three Mile Island Unit 1), which received a $1bn loan, and the Palisades nuclear power plant in Covert Township, Michigan, which secured a $1.52bn loan.

“President Trump has set an ambitious course to restore American nuclear leadership, and the restart of Duane Arnold Nuclear Plant in Iowa marks another step in advancing America’s nuclear renaissance,” said US deputy secretary of energy James P. Danly. “Returning 615MW of reliable baseload generation will drive down electricity costs, while supporting thousands of American jobs. This administration is pursuing a comprehensive nuclear strategy, restarting existing reactors, increasing the output of our nuclear fleet, and accelerating new construction, to build the abundant, affordable, and reliable power system required for American prosperity and reindustrialization.”

The plant is one of several to have its capacity contracted to a hyperscale data center firm. In addition to Google and Microsoft, Meta signed a 20-year PPA with Constellation Energy for the entire output of the 1.1GW Clinton Clean Energy Center in Clinton, Illinois. AWS has also gotten in on the act, signing a 1.92GW PPA with Talen Energy for energy from the 2.5GW Susquehanna nuclear power plant in Pennsylvania.

登录即免费解锁1,984字全文

因资讯版权原因,登录长桥账户后方可浏览相关内容
感谢您对正版资讯的理解与支持

推荐阅读

  • 2025年10月28日 06:47美国核电复兴提速:谷歌与 NextEra 签 25 年购电协议,关闭 5 年的核电站” 起死回生”
  • 2025年5月23日 00:41特朗普减税法案削减税收抵扣,美国光伏股暴跌,核电股上涨

关联股票

新纪元能源

新纪元能源

USNEE

-0.52%

谷歌-A

谷歌-A

USGOOGL

谷歌-C

谷歌-C

USGOOG

LongbridgeAI