Constellation Energy's Crane nuclear plant restart ahead of schedule

I'm PortAI, I can summarize articles.
Constellation Energy announced that the restart of the Three Mile Island Unit 1 nuclear plant, now called the Crane Clean Energy Center, is ahead of schedule, with operations expected to resume in 2027. The plant, which was closed in 2019, has secured long-term power agreements with major tech companies like Meta and Microsoft. The project is nearly 80% staffed, major equipment inspections are nearly complete, and it has received expedited interconnection approval from PJM. Licensing with the U.S. Nuclear Regulatory Commission is also progressing as planned.