"The situation has escalated rapidly," within just three months, 8 projects have been stalled and 9 projects have been delayed! The American public is "resisting" the data center frenzy

I'm LongbridgeAI, I can summarize articles.
Data shows that from March to June 2025, opposition from American communities led to the blocking or delaying of data center projects valued at $98 billion, far exceeding the previous total of $64 billion over nearly a year. This resistance sentiment is crossing party lines, with project delays occurring in Democratic-led Virginia as well as Republican strongholds Indiana and Kentucky. However, the current investment enthusiasm driven by AI among tech giants remains unabated