"China may not be able to do it"! AI bubble fills Texas: Over 220GW large projects applied to enter the grid by 2030

Wallstreetcn
2025.12.12 22:32
portai
I'm PortAI, I can summarize articles.

The Texas grid management agency ERCOT reported that the total capacity of large projects applying to connect to the Texas grid before 2030 has exceeded 220 GW, more than double the peak demand in the state this summer, with over 70% being data centers. The number of large projects applying for power interconnection in Texas this year has nearly quadrupled, with more than half, approximately 128 GW of projects, yet to be submitted for ERCOT review