NET Power Withdraws MISO Interconnection Request

TradingView
2026.01.05 21:33
portai
I'm PortAI, I can summarize articles.

On December 29, 2025, NET Power Inc. announced its withdrawal from the MISO interconnection request due to higher costs. Key Highlights: NET Power withdraws due to increased network upgrade costs.The company retains its site lease in northern MISO.Exploring alternative clean power generation options.No significant financial impact expected from withdrawal.Original SEC Filing: NET Power Inc. [ NPWR ] - 8-K - Jan. 05, 2026DisclaimerThis is an AI-powered summary. It may contain inaccuracies. Consider verifying important information with the source. Please note this summary is solely based on documents filed with the SEC.