COSCO advances Jurong Island logistics hub phase II works

Singapore Business Review
2026.06.15 04:10
portai
I'm LongbridgeAI, I can summarize articles.

COSCO SHIPPING International (Singapore) reported that structural works at the Jurong Island Logistics Hub Phase II have reached the sixth and seventh floors. Other construction activities, including flooring, fire-fighting equipment, and plumbing, are progressing smoothly. Warehouse racking and crane installations have commenced in preparation for operations upon obtaining the Temporary Occupation Permit. COSCO is also demolishing part of Phase I to connect it with Phase II while maintaining ongoing operations.