FirstEnergy Launches $28 Million Grid Upgrade in Southeastern Pennsylvania

I'm PortAI, I can summarize articles.
FirstEnergy Corporation is investing $28 million to upgrade the power grid in southeastern Pennsylvania, benefiting residents and businesses in Lehigh and Berks counties. The project includes rebuilding 15 miles of high-voltage power lines and upgrading four substations. This initiative is part of the Energize365 program, with FirstEnergy planning to invest $28 billion between 2025 and 2029 to modernize its electric grid. Construction began in August and will be completed by November 2027.