Energy Fuels' U.S. Rare Earth Processing Expansion Boasts Lower-Than-Expected CAPEX, Significant Annual EBITDA, and Among the Lowest Cost NdPr Production in the World | UUUU Stock News

StockTitan
2026.01.15 03:15
portai
I'm PortAI, I can summarize articles.

Energy Fuels Inc. announced a Bankable Feasibility Study (BFS) for its Phase 2 circuit expansion at the White Mesa Mill in Utah, confirming a capital cost of $410 million and a production cost of $29.39/kg NdPr. The expansion aims to produce over 6,000 tpa of NdPr, positioning Energy Fuels as a leading U.S. rare earth producer. The BFS projects an annual EBITDA of $311 million for the first 15 years, with a combined NPV of $3.7 billion when including the Vara Mada project. Regulatory approval is expected by mid-2027, with construction planned for Q1 2029.