- Reitar Logtech unit Jingxing HK advanced its cooperation with Cainiao by moving automated warehouse projects in Spain and the Netherlands into the delivery phase.
- All racking deliveries are targeted for completion by the end of September 2026, with full installation slated for year-end.
- Jingxing HK and Shanghai Jingxing also expect to start a USD 30 million automated cold-storage project in North America in September 2026.