From 18 GW to 52 GW! Goldman Sachs Predicts US AI Infrastructure Acceleration Through 2028, Sparking Unprecedented "Power Bull Market"

LongbridgeAII'm LongbridgeAI. Here is the key information I extracted
- Goldman Sachs projects that US AI data center power capacity additions will surge to 18 GW in 2026, 28 GW in 2027, and reach a record 52 GW by 2028.
- This unprecedented power expansion is driven by increasing facility counts, larger single-building sizes, and higher power densities concentrated in key regional markets like PJM and ERCOT.…
Disclaimer

According to Zhitong Finance APP, although the construction progress and permitting for large-scale AI data centers in the US may be significantly delayed following the Democratic Party's victory in the midterm elections, Wall Street financial giant Goldman Sachs recently extended its power capacity forecast for US data centers to 2028 in a newly released research report. It predicts an additional 52 gigawatts (GW) of capacity in that year, nearly triple the incremental addition expected in 2026. If the 52 GW scheduled for 2028 comes online as planned, it will break the record for the largest annual increase in power capacity for US data centers, representing approximately three times the incremental growth Goldman Sachs forecasts for 2026. By comparison, Goldman Sachs expects new additions of 18 GW and 28 GW in 2026 and 2027, respectively. Previously, US data centers added an average of about 4 GW annually from 2021 to 2024, with approximately 10 GW added in 2025.

Just as Goldman Sachs released this report covering power capacity forecasts, global stock markets saw a sharp decline in the AI computing power and semiconductor rally triggered by Jensen Huang regaining control at NVIDIA, merely one day after the surge. As of market close on November 24 (US Eastern Time), NVIDIA shares rose 31.48% on Monday, adding approximately $952 billion to its market capitalization in a single day, setting a record for the largest single-day market cap increase for a listed company in the US and globally. The most intense capital inflow on Monday was seen in technology stocks heavily weighted towards AI computing power and semiconductors, which had previously led the decline—the NASDAQ-100 Index rose 6.86%, with the cumulative market capitalization of its constituent companies rebounding by over $2 trillion. Additionally, the Philadelphia Semiconductor Index, which includes chip giants like NVIDIA and AMD, and US-based memory chip giant Micron Technology rose 14.03% and 19.04%, respectively.

However, by the close of US trading on Tuesday, the S&P 500 fell 0.50%, the Nasdaq Composite Index dropped 1.48%, and the Philadelphia Semiconductor Index plunged 7.88% to 8,832.50 points. Micron, AMD, and NVIDIA fell 11.01%, 8.86%, and 5.86%, respectively. On Wednesday, selling pressure spread to South Korea and the broader Asian technology sector. The two largest memory chip giants globally, Samsung and SK Hynix, both fell more than 6% in early trading. The Korea KOSPI 200 futures dropped 5.12%, triggering the Korea Exchange's five-minute pause on programmatic sell orders (side-car mechanism), while spot market trading continued.

Following the US midterm elections, policy changes in states such as Texas, Ohio, and Georgia may slow down some large-scale data center projects that have not yet started construction. In its report released on November 24, Goldman Sachs firmly extended its power demand expansion forecast to 2028. After adjusting project schedules based on historical delays and cancellations, it predicts that US data centers will add a maximum power capacity of 52 GW in 2028, nearly triple the 18 GW incremental addition expected for 2026. Approximately 26 GW of this capacity had not yet started construction at the time of the report's release. Whether the data center power expansion capacity in 2028 can reach this scale largely depends on whether these projects can obtain approval, start construction, and connect to the grid on schedule.

Why is the Scale of Large-Scale AI Data Center Construction in the US Accelerating from 18 GW to 28 GW and Then to 52 GW?

Goldman Sachs expects the maximum new power capacity for US data centers to rise from 18 GW in 2026 to 28 GW in 2027, and then jump to 52 GW in 2028. The increase in the number of server rooms, the expansion of individual building areas, and the higher power density per unit area collectively drive up power supply demand. Of the capacity expected to be added in 2028, approximately 35 GW is concentrated in three major electricity markets: PJM, Texas ERCOT, and the Midwest MISO. About 26 GW had not yet started construction at the time of the report's release.

The key to this surge in power capacity lies in whether AI server clusters coming online after projects are energized on schedule can bring sustained, full-load power consumption. If the load ramps up as expected, power supply and demand in core regions will tighten further, and the power generation and natural gas consumption of gas-fired units are also expected to increase. This is a crucial bullish rationale for Goldman Sachs' positive outlook on US Henry Hub natural gas prices from 2028 to 2030 and its optimism regarding the data center power equipment supply chain.

In the view of Goldman Sachs' analyst team, the actual incremental growth this year has already exceeded the baseline levels of previous years. By the end of October 2026, the maximum power capacity of US data centers increased by 12 GW year-over-year, a 33% rise. Goldman Sachs estimates that this corresponds to an average increase in power demand of about 9 GW, more than double the average annual increment of 4 GW from 2022 to 2025. Compared with national data from the US Energy Information Administration (EIA) as of August, data centers contributed more than one-third of the total increase in US power demand. Among the three regional electricity markets, capacity in PJM, Texas ERCOT, and Midwest MISO increased by 4.4 GW, 2.4 GW, and 2.1 GW year-over-year, respectively.

Image

Image

Goldman Sachs expects new capacity additions of 18 GW, 28 GW, and 52 GW in 2026, 2027, and 2028, respectively. It forecasts approximately 10 GW of new additions in 2025, with an annual average of about 4 GW from 2021 to 2024. Goldman Sachs has revised its end-2027 capacity estimate upward from 90 GW to 92 GW, representing a 44% increase compared to the end of 2026. Based on the annual increments in the report, the total capacity by the end of 2028 is projected to be approximately 144 GW.

Compared to 2026, the additional ~34 GW in 2028 stems from three changes: more newly operational buildings contributing 15.9 GW; higher power density per unit area contributing 9.5 GW; and larger individual building sizes contributing 9.0 GW. Calculated across all operational buildings, the average capacity per building increased from 16 MW in 2020 to 31 MW in 2026, and is expected to reach 49 MW in 2028, with even higher averages for newly constructed buildings. Goldman Sachs expects the annual growth rates for single-building area and power density to accelerate from approximately 6% each in previous periods to 11% and 14%, respectively.

Image

Image

About Half of the 52 GW Has Not Yet Started Construction: Where Are the Operational Risks Concentrated?

The 52 GW figure is a project forecast adjusted for historical fulfillment rates. Since May 2026, Goldman Sachs has modeled schedules using Aterio data, incorporating projects that have started construction as well as those meeting key conditions such as financing, permitting, grid interconnection agreements, land rights, and water rights. It then applies adjustments based on historical delays and cancellations. The Goldman Sachs model predicts that about 60% of the scheduled capacity will come into commercial operation on time within the next 12 months, and about 50% within two years.

Assuming a construction cycle of approximately two years, most projects scheduled to be operational before the third quarter of 2028 have already started construction. For capacities scheduled thereafter, less than half have reached the physical construction stage. Based on the model's projected operational capacity, about 5 GW scheduled for 2027 had not yet started construction, rising to about 26 GW for 2028. These 26 GW are included within the 52 GW forecast and directly impact the fulfillment rate for 2028.

Expansion remains concentrated in core electricity markets. In 2028, Virginia and Texas are expected to contribute a combined 19 GW, accounting for about 36%. PJM, ERCOT, and MISO together will contribute 35 GW, representing about 68%. As shown in the charts below, while the total volume of unstarted capacity nationwide in 2027 is limited, the proportion within specific states such as Florida, Kansas, Tennessee, and Arizona is relatively high. By 2028, the unstarted capacity in Texas, Virginia, and Arizona is estimated to be approximately 6.4 GW, 3.2 GW, and 2.8 GW, respectively.

Image

Image

Risks may further fall on regional grids. Among the capacity scheduled to be operational in 2028, the proportions not yet started in PJM, ERCOT, and MISO are 55%, 45%, and 40%, respectively. For the Southwest Desert, Southeast Georgia, Northwest, and SPP regions, these figures are 68%, 55%, 73%, and 38%, respectively. Goldman Sachs believes that behind-the-meter power, modular delivery, and accelerated construction can improve fulfillment rates. However, policy changes following the midterm elections and community resistance in places like Virginia and Arizona could cause delays beyond historical adjustment rates. The charts below track the concentration of new capacity in leading states and regional grids.

Image

Image

How Does the 52 GW Figure Transmit to the Data Center Power Chain, Gas Usage for Power Generation, and Gas Prices?

Goldman Sachs' natural gas baseline originally accounted for only 28 GW of new data center power capacity annually. Its natural gas model for 2027–2035 assumes that data centers will increase average power load by 18 GW annually, equivalent to adding about 28 GW of maximum power capacity each year, consistent with the medium-term estimates of the Goldman Sachs equity research team. The schedule forecast for 2027 is close to this baseline, while the 52 GW for 2028 is significantly higher.

If projects are energized on schedule and loads ramp up as servers come online, regional power supply and demand will tighten further, creating room for upward revisions in gas usage for power generation. This supports Goldman Sachs' bullish stance on Henry Hub natural gas prices from 2028 to 2030. The chart below compares the two sets of forecasts; differences in the 2025 historical values stem from differing data methodologies between Aterio, S&P, and the Lawrence Berkeley National Laboratory.

Image

This Goldman Sachs report helps explain why, despite the sharp decline in the AI computing power and semiconductor sectors and the expectation of delayed data center construction under the pressure of rising AI financing costs, power demand forecasts can still be revised upward. The AI computing power and semiconductor themes reprice orders, pricing, and margins almost daily, whereas the realization of power projects is determined by the unprecedented urgency of energization, data center construction schedules, grid interconnection, and equipment commissioning. For investors, the most identifiable milestones are project commencement, finalized power supply arrangements, actual energization of server rooms, and load ramp-up. These nodes determine when the scheduled GW translates into utility sales volume and actual fuel consumption at gas-fired power plants.

Image

AI training and inference workloads expand power consumption through different paths. On the training side, larger clusters and more experiments drive up the installed base of accelerators and their operating hours. On the inference side, consumption depends on call volume, tokens consumed per task, and how many requests servers can handle simultaneously. Long inference tasks and multi-turn agent tasks may repeatedly call models, generating more tokens and potentially reducing concurrency efficiency. Chip upgrades, quantization, and batch processing can reduce energy consumption per unit of computation. Whether total power consumption continues to grow rapidly depends on whether the growth in task volume and computational load per task outpaces the reduction in energy consumption per unit.

From chips to electricity meters, conversion involves two stages: utilization rates and server room losses. The data center super-grid system handles the full-station load of GPUs, CPUs, networking, storage, plus cooling and power distribution losses. According to Goldman Sachs' methodology, maximum power capacity is roughly equivalent to IT equipment power capacity multiplied by Power Usage Effectiveness (PUE). For example, for a server room with an IT capacity of 100 MW, if the average IT load is 80 MW and the PUE is 1.2, the average full-station load is about 96 MW, resulting in annual electricity consumption of approximately 0.84 terawatt-hours (TWh). Therefore, the 52 GW figure answers how much power supply capacity needs to be configured. The speed of equipment rack-up, utilization rates, and actual operating hours determine how much electricity is ultimately sold.

Source: Zhitong The copyright of this article belongs to the original author/organization.

The views expressed herein are solely those of the author and do not reflect the stance of the platform. The content is intended for investment reference purposes only and shall not be considered as investment advice. Please contact us if you have any questions or suggestions regarding the content services provided by the platform.