'The US Is Running on Empty,' Warns Economist Steve Hanke as China Adds Nearly 10x More Power Capacity Than America in 2025 Amid AI Boom

LongbridgeAII'm LongbridgeAI, I can summarize articles.

Economist Steve Hanke highlighted China’s rapidly expanding power capacity, which comes as the U.S. and China compete to meet rising electricity demand amid the AI boom.

Hanke took to X on Thursday and stated that China added 543 gigawatts of power capacity in 2025, nearly 10 times the roughly 60 gigawatts added by the U.S.

"The US is running on empty," Hanke wrote, citing an Apollo chart showing China’s annual capacity additions accelerating since 2022.

Apollo’s chart shows China adding nearly 550 GW of power capacity in 2025, compared with roughly 60 GW in the U.S. China’s annual additions have surged since 2022, widening the gap with the U.S. to nearly 10-fold as the AI boom intensifies competition for electricity.

China added 543 GW of new power capacity in 2025.

That is close to 10 TIMES what the US added.

THE US IS RUNNING ON EMPTY. pic.twitter.com/dvnoCBWDwb

— Steve Hanke (@steve_hanke) November 26, 2026

Read Also: Economist Steve Hanke Questions AI ‘Hype’ as Just 2.9% of US Consumers Pay for ChatGPT, Claude, Gemini or Grok: ‘The Public Is Not Buying’

AI Boom Runs Into Power Constraints

The Apollo report echoed Hyliion CEO Thomas Healy, who told Benzinga in June that electricity generation, rather than access to advanced chips, could determine the winner of the global AI race as data centers drive soaring power demand. He highlighted China’s addition of approximately 500 gigawatts of electricity capacity last year, compared with just 50 gigawatts in the U.S., a tenfold gap.

In November 2025, investor Kevin O’Leary warned that China’s rapid power generation expansion poses a major threat to U.S. leadership in AI. He argued that China can build power infrastructure quickly, including coal plants, with fewer regulatory hurdles, while U.S. projects face lengthy approvals and grid constraints.

Nvidia Corp. (NASDAQ:NVDA) CEO Jensen Huang had also echoed similar concerns, pointing to China’s cheaper, subsidized electricity and faster regulatory processes as potential advantages in the AI race.

US Ramps Up Gas Power and Permitting

That being said, Global Energy Monitor (GEM) reported in August stated that the U.S. has overtaken China in new gas-fired power plant construction, driven by surging electricity demand from AI data centers.

According to the report, U.S. gas projects under construction rose 76% in the first half of the year, while total capacity under development jumped 50% to 378 GW. Completing all proposed projects would cost more than $647 billion, expand the U.S. gas fleet by roughly two-thirds and potentially increase power-sector emissions by up to 20%.

Last week, the Senate advanced a major permitting reform bill to the House, aiming to accelerate U.S. energy and infrastructure projects, including power transmission lines. The legislation would shorten environmental reviews, allow federal regulators to approve transmission projects when states fail to act, and limit legal challenges to 150 days after approval.

Disclaimer: This content was partially produced with the help of AI tools and was reviewed and published by Benzinga editors.

Read Also: Elon Musk’s SpaceX Could Make ‘Biggest Fortunes’ From AI Without Winning the AI Race: Eric Jackson Explains How

Image via Shutterstock

Login to unlock2,239characters for free

Due to copyright restrictions, please log in to your Longbridge account to view this content.
Thank you for your understanding and support of licensed content.