現有電廠是數據中心供電的 “基石”:Constellation CEO

ZeroHedge
2026年8月8日 下午04:51
LongbridgeAI我是 LongbridgeAI,我可以總結文章信息。

Constellation Energy 首席執行官 Joseph Dominguez 表示,現有的發電廠是為數據中心提供電力的 “基石”,反對等待新一代發電設施。該公司強調了可用的輸電能力,並計劃通過電池管理峯值需求。此外,Constellation 將其 606 兆瓦的 Brazos Valley 發電廠以 8.6 億美元的價格出售給 LS Power,以滿足 Calpine 的和解義務,同時報告第二季度調整後每股收益為 2.55 美元

By Ethan Howland of UtilityDive.com

Despite the Ratepayer Protection Pledge’s call for planned data centers to supply their own new generation, existing power plants will play a major role in supplying them with power, according to Joseph Dominguez, Constellation president and CEO.

“We’re never going to build this economy if … we have to wait for new power plants to be built before we can connect any data center,” Dominguez said Thursday during an earnings conference call. “The bedrock of building out at least this early phase of the data economy is going to rely heavily, in my view, on existing generation.”

Dominguez said there is significant available capacity in the transmission and generation system that can serve consumers more than 99% of all hours in a year.

“We have a peak capacity concern, not an energy concern,” he said. “The secret sauce here is to deal with the handful of peak hours that present reliability concerns, and at the same time to harvest the stranded capacity that exists every other hour of the year.”

The peak periods can be managed with batteries, demand response and peaking resources, according to Dominguez.

“[Potential customers] still have to figure out not just the peak, but what they’re doing every other hour of the year,” he said. “That’s where our fleet becomes extraordinarily valuable because it’s a fixed-price, clean energy resource that they could count on for decades.”

Constellation Energy’s 2,347-MW Byron nuclear power plant near Byron, Ill. The Baltimore-based company’s nuclear fleet could be increased by 1.1 GW through uprates, according to an Aug. 6, 2026, earnings presentation

The Baltimore-based independent power producer owns about 55 GW of generation, including about 22 GW of nuclear capacity.

Constellation has several projects that are tied to data centers that have been affected by the pause in Texas’ Batch Zero interconnection process, according to Dominguez.

The company doubts the state’s audit of proposed data centers will take long.

“All these folks, particularly coming into the midterm elections, they want to be responsive to their constituents, and Gov. [Greg] Abbott has asked for some pretty reasonable information to be included as part of Batch Zero,” Dave Dardis, chief of external affairs and growth officer, said on the conference call.

With large load interconnection requests — mostly data centers — totaling about 474 GW, Abbott asked that planned data centers provide information about their power supplies, expected electric and water use, and amount of public financial assistance.

The information can be provided quickly, and Constellation doubts there will be a “meaningful delay,” according to Dardis.

“We see this as a temporary measure that we think is manageable by the industry,” he said.

By the numbers: Constellation Energy Q2 ’26

  • $860M: The sale price for LS Power’s planned purchase of Constellation’s 606-MW, gas-fired Brazos Valley power plant in Texas.
  • ~1.1 GW: Potential uprates for Constellation’s 22-GW nuclear fleet.
  • $2.55/share: Second-quarter adjusted operating earnings, up from $1.91/share a year ago, driven by the Calpine purchase, higher capacity revenue and other factors.

Meanwhile, Constellation expects the currently low wholesale power prices in ERCOT will rebound when data centers start coming online, according to Dominguez.

Battery storage and other resources are driving down electricity prices by coming online before the expected load, he said.

“The market will start to tighten up as data centers get built, and you start to see the market come into more or less equilibrium,” Dominguez said.

Also in Texas, after a bidding process, Constellation sold its 606-MW gas-fired Brazos Valley power plant to LS Power for $860 million, or about $1,420/kW.

“It was clear from a very competitive process that buyers recognize the long-term value of gas-fired assets with the potential for even higher utilization rates,” Shane Smith, Constellation CFO, said.

Once approved, the power plant sale will satisfy the Constellations settlement obligations for its Calpine purchase, he said.

The assets that Constellation had to sell under the agreement with the U.S. Department of Justice are expected to produce about $5.9 billion in gross proceeds, he said.

登錄即免費解鎖3,757字全文

因資訊版權原因,登錄長橋賬戶後方可瀏覽相關內容
感謝您對正版資訊的理解與支持

推薦閱讀

  • 2026年9月10日 早上08:54蘋果:存儲暴漲逼提價,摺疊屏能救場嗎?
  • 2026年9月10日 早上08:58甲骨文第一季度財報前瞻:股價較歷史高點下跌53%,分析師建議買入並持有——“十年股”
  • 2026年8月20日 早上07:56英偉達芯片密集的數據中心需要比任何公用事業公司所能提供的更多電力。那麼,誰才是真正的贏家呢?
  • 2026年7月4日 晚上06:20人工智能的發展離不開這隻股票(提示:並非英偉達)
  • 2026年4月13日 下午01:12美國最大電網 PJM 發佈 “緊急提案”:擬增 15 吉瓦電力,以應對 AI 數據中心浪潮

關聯股票

Constellation Energy

Constellation Energy

USCEG

-1.72%

Tradr 2X Long CEG Daily ETF

Tradr 2X Long CEG Daily ETF

USCEGX

LongbridgeAI